Plan a containment and check its airflow

Lay out the containment, chambers, zip doors and negative air machine, and see which way air moves through every door and gap before you build it. About 10 minutes.

For: CaseLens Pro, in a web browser (pro.caselensapp.com) · Last reviewed:

Watch it (2:23, no sound)

Before you start

Step by step

  1. 1Open the Containment & airflow tab

    Open the job and click the Containment & airflow tab. It explains what the calculation does and its limits. Click Start a plan. (If you have the job's DocuSketch or Xactimate sketch, see the guide on importing a sketch instead.)

    Open the Containment & airflow tab
    Tap the picture to see it full size.
  2. 2Add the containment

    Under Spaces, click Add a space. Name it, set Role to Containment (work area under negative air), and enter its Length, Width and Height in feet (or the volume if you know it).

    Add the containment
    Tap the picture to see it full size.
  3. 3Add the chambers and the house

    Click Add a space again for each decon chamber, with Role set to Transition chamber (here Dirty chamber and Clean chamber, 4 × 4 × 8 ft). Then add the rest of the house as one space with Role set to Occupied / unaffected area. For the house, a volume is easiest (floor area × ceiling height, for example 1,500 sq ft × 8 ft = 12,000 cu ft).

    Add the chambers and the house
    Tap the picture to see it full size.
  4. 4Add the doors between spaces

    Under Doors, openings, leakage and machines, click Add a connection. Set What it is to Door or zip door (closed, with gaps), choose the two spaces it joins under Between and And, and enter the Gap area when closed in square inches, plus the door's width and height for when it's held open. The hint under each kind explains how to estimate it.

    Add the doors between spaces
    Tap the picture to see it full size.
  5. 5Add the leaks and the house's leakage

    Add the leakage through the plastic and walls as Leakage (seams, penetrations) in square inches, and the house's leakage as Building leakage to outdoors (blower door) using its blower-door CFM50 (a rough guess if it wasn't tested). These numbers decide how strongly the machine pulls air in, so use measured values when you can.

    Add the leaks and the house's leakage
    Tap the picture to see it full size.
  6. 6Add the negative air machine

    Click Add the 1 air scrubber on site to bring in the machines from the job's Equipment log (here Example 500 CFM unit), or add a connection with What it is set to Negative air machine / exhaust fan. Set it to take air from the containment (Takes air from) and blow it Outdoors (Blows it into). Under Airflow (CFM), enter the airflow you actually get: a machine's rated CFM is usually higher than what it moves with loaded filters and ducting.

    Add the negative air machine
    Tap the picture to see it full size.
  7. 7Set the way out

    Under Egress route, pick each space from the list in the order workers walk out: the containment first, then each chamber, then where the route leaves (here the rest of the house). Each door on the route is also calculated held fully open.

    Set the way out
    Tap the picture to see it full size.
  8. 8Set the target, save and calculate

    If the responsible professional set a target, enter it at the top under Target: containment at least this far below each space next to it and pick the Target units (in. w.c. or Pa); here 0.02 in. w.c. Then scroll down and click Save plan, then Calculate. The calculation runs on your own device with the NIST CONTAM airflow engine, for all doors closed and with each egress door held open. It takes a few seconds.

    Set the target, save and calculate
    Tap the picture to see it full size.
  9. 9Read the results

    Under Calculation you see each space's pressure and which way air moves through every door and gap. A step passes (Inward only) only when no air moves away from the containment. If you set a target, each space next to the containment shows Meets or Below target: here the containment is only 2.02 Pa below the dirty chamber, under the 5.0 Pa target. Results are labeled Computed: they follow from your inputs and aren't measurements.

    Read the results
    Tap the picture to see it full size.
  10. 10Compare with your manometer

    Once it's built, measure the pressure across the containment with a manometer and add it under Manometer readings → Add a reading (negative means the space is lower), with the instrument and the conditions. Click Save reading. CaseLens lists it, labeled Observed, next to the calculated value and the difference. A big difference usually means an input is off: a gap, the machine's real airflow, or the house leakage.

    Compare with your manometer
    Tap the picture to see it full size.

If something goes wrong

A space next to the containment says Below target
The containment isn't far enough below that space. Add airflow (a second machine, or a bigger one), or tighten the gaps between them (seal the poly seams, tape the zip door), then click Calculate again.
The results say Check inputs instead of a pass
The machine would have to work against more pressure than is realistic (over 0.5 in. w.c.). Check the machine's airflow and the gap areas; a containment sealed tighter than real life does this.
The results say Out of date
You changed the plan after calculating. Click Calculate again.
Both ways through an open door
Warm and cool air swap through a doorway even with the machine running (warm out the top, cool in the bottom). Keep doors closed except to pass through, or add a chamber.
It won't calculate
The message lists what's missing, for example a space with no size or a connection with no second space. Fix those and calculate again.